Palm Beach County zoning staff approve more data center space at Project Tango site
An administrative approval lets the 202-acre site at 20-Mile Bend hold 698,000 square feet of data centers, three months after commissioners rejected a larger plan.

- → The county zoning director approved on October 7 a reassignment of uses within the site's existing master plan, needing no commission vote 1.
- → Permitted data center space rises from 200,000 to 698,000 square feet; 1.2 million square feet of warehouses is unchanged 1.
- → In July commissioners voted 5-1 against a plan for about 1 million square feet of data centers 1.
- → The approval carries an 850-foot no-data-center buffer, sound studies, noise monitoring and closed-loop cooling 1.
Palm Beach County's zoning director has approved a request that more than triples the data center space allowed on the Project Tango site at 20-Mile Bend, without a vote of the county commission 1.
The 202-acre site lies north of Southern Boulevard in unincorporated Palm Beach County, with the Arden community to the east. PBA Holdings owns most of it 1. Its existing master plan already allowed 200,000 square feet of data center space and 1.2 million square feet of warehouses, with about 600,000 square feet left unassigned 1.
What the October 7 approval allows
| Use | Square feet |
|---|---|
| Data center building 1 | 288,000 |
| Data center building 2 | 288,000 |
| Data center building 3 | 122,000 |
| Total data center | 698,000 |
| Warehouses (unchanged) | 1,200,000 |
| Support offices and utility building | 122,000 |
Zoning Director Wendy Hernandez approved PBA Holdings' request on October 7 to assign the unassigned space to data centers, bringing the total to 698,000 square feet 1. The plan shows two data center buildings of 288,000 square feet each and one of 122,000 square feet. Warehouses stay at 1.2 million square feet, and support offices and a utility building use the remaining 122,000 square feet 1. The approval is final unless challenged in court 1.
Because the change reallocates development rights already in the master plan rather than adding new ones, it did not go back to commissioners 1. In July, PBA had sought about 1 million square feet of data center use and roughly 1.6 million square feet of added development; the commission rejected that request 5-1 on July 15 1.
Conditions and pending disputes
Staff attached conditions first proposed in July: an 850-foot buffer along the eastern property line where no data centers may be built, sound studies, continuous noise monitoring and a closed-loop water cooling system 1. The buffer would block a plan by WPB Logistics Owner, which holds an option on land along the eastern edge, to convert its 1.2 million square feet of warehouses to data centers. The two landowners are in a legal dispute 1.
PBA Holdings has also appealed the July rejection under Florida's Land Use and Environmental Dispute Resolution Act; no special magistrate hearing date had been set 1. The commission adopted a one-year moratorium on new data center applications in August and was set to vote on paying up to $225,000 to consultant VHB to help rewrite zoning rules for hyperscale AI data centers 1. Residents opposed to the project called the staff approval a way around the July vote and the moratorium 1.